Reuse and save in excess of US$ 80M

F3-FA platform brokerage and auction

Spirit Energy NL appointed us to promote the reuse of the Self Installing Gas Platform F3-FA.

The facility was installed in 2010 and is scheduled to be removed from the offshore location in the summer 2019.

The platform, specially designed for re-use, is a Self-Installing Platform type 2 (SIP-2) with a substructure supported by suction piles

The topside facilities comprises full separation, gas drying and compression facilities, designed for handling 92 MMSCFD gas, 2,500 BPD condensate and 940 BBPD water.

The F3-FA platform can be inspected at the quayside in the Netherlands and is planned to be offered through an auction.

Reuse and save in excess of US$ 80M.++ and have FIRST GAS twelve months ahead of schedule.

Please have a look at F3-FA project Linkedin page for details:  https://lnkd.in/d_dczv9    

 

 

 

 

 

 

 

 